Configure imported Equipment Sequence properties
When an
Equipment Sequence
is imported, the configuration properties on the Details pane of the Import Configuration
dialog box may require adjustment.To adjust configuration properties for an imported
Equipment Sequence
:- On theFilemenu, selectImport Component > Equipment Sequence.
- In theImport Equipment Sequencedialog box, select the sequence to import.
- SelectOpen.
- In theImport Configurationdialog box, select theOperationsetting for the import.The Operation setting chosen depends on whether the Import Name exists in the project.If the Import Name is used as a program name in the project, setOperationtoUse ExistingorOverwrite.If the Import Name is not used in the project, setOperationtoCreateorDiscard.
- Use Existing: Specifies that existing settings in the project are used, not the settings in the imported component.
- Overwrite: Specifies that settings in the import file will overwrite the information in the project file, as long as overwriting is a permitted operation.
- Create: Specifies that a new component is created in the project based on the information in the import file, as long as creation is a permitted operation.
- Discard: Operation defaults toDiscardwhen do not have adequate security privileges to import the file, or if the import file conflicts with the existing project. If the import file conflicts with the existing project, try changing theFinal Namesetting to continue the import. If the import does not complete, check security privileges.
- (optional) To change the name of the imported file, or if the imported file name conflicts with the existing project, type aFinal Namefor the imported file. By default, theFinal Nameis the name of the import file.
- (optional) When theOperationis set toCreate, select thePropertiesbutton to view the basic settings for the importedEquipment Sequence.
- (optional) SelectCollision Detailsto find differences between the imported file settings and the existing settings.
- (optional) InDescription, type a description for the import file. IfOperationis set toUse ExistingorDiscard, theDescriptionbox is not available.
- (optional) On theSchedule Inmenu, select a program location for theEquipment Sequence. To unschedule theEquipment Sequence, selectUnscheduled. To schedule theEquipment Sequence, select a task.
- (optional) On theParentmenu, select a parent for the importedEquipment Sequence. Use theParentsetting to group programs hierarchically in theLogical Organizer.
- (optional) SelectInhibit Equipment Sequenceto prevent theEquipment Sequencefrom being owned and commanded by another user or program after it is imported.
- (optional) SelectPreserve existing tag values in offline projectto prevent tag values in the project from being overwritten by an import theEquipment Sequencein offline mode. Note that tag values are never overwritten when importing anEquipment Sequencewhile online with the controller.
- SelectOK.
Provide Feedback