Loading
Case Study | Mining
Recent ActivityRecent Activity
閱讀時間8分鐘

Scheduling and Planning with Mine Models

Arena reduces costs and improves operations at Vale site in South America.

分享:

LinkedInLinkedIn
XX
FacebookFacebook
PrintPrint
EmailEmail
Mining worker communicating with others outside of facility

Challenge

To correctly analyze and generate short-term planning schedules, or simply month mining plan.

Solutions

This optimization model runs each time that the simulator program begin, to produce initial allocation of the loader and transportation equipment. This model will also run during the simulation, when equipment and/or a truck failure may happen, seeking a new optimal allocation for shovel and remaining trucks. It will also generate shovels allocation to different mining areas and will calculate amount of trips that each truck should take to each area, to reach production goal.

Results

A scenario was generated to compare a monthly plan with and without quality/grade constraints. Optimization model sensitivity was tested against the amount of ore production. The results demonstrate that production decrease while quality variability increases (see Figure 5 & Figure 6 within the paper). It can be explained due to successive loader changes (from each mining area) to try to keep quality control.

Background

Vale is the world’s second-largest mining and metal company in market value, with assets of more than US$ 100 billion. It is the world leader in production and export of iron ore and pellets and an important producer of nickel, copper concentrate, bauxite, alumina, potassium, kaolin, manganese and iron alloys.

Vale is also the biggest logistics service provider in Brazil, developing complete solutions by interlinking railways, ports and its own sea terminals. Models were applied and approved at Vale’s Aguas Claras Mines complex and currently are used for planning purposes.

The objective is to provide to the mine feasible goals for quality and quantity production of ROM (Run of Mine). This is critical, because a goal lower than possible represents profit loose for the company and a goal higher than possible have many serious consequences, since the mine managers are evaluated based on the accomplishment of that goals.

Challenge

The objective is to provide to the mine feasible goals for quality and quantity production of ROM (Run of Mine). This is critical, because a goal lower than possible represents profit loose for the company and a goal higher than possible have many serious consequences, since the mine managers are evaluated based on the accomplishment of that goals.

Solution

A discrete-event simulation model is able to reproduce the randomness of the equipment problems and the time variation of the trips and processes. This makes simulation a good tool to check the feasibility of the plan. But a simulation model itself is not able to precisely represent through heuristics some complex decisions logic that are used to choose the best the trip plan at each process interference. Then it is absolutely necessary planning the number of trips using the optimization model.

However, the use of optimization model as a procedure of simulation model allows a more realistic simulation. At the beginning of the simulation, the optimization model is run in order to calculate the initial shovel allocation and the schedule truck trips. After that, the simulation model is run until a system state change (failure in any equipments or lack of material in any mining area). The simulation model calls the optimizer procedure to calculate the new optimization and so on. The proposed solution is the integration of both tools: discrete-event simulation and optimization, not as a post or pre-simulation run, but as a combined run.

Results

Main objective was achieved, that was to reduce mining costs, through simulation and optimization usage in mining planning. Presented solution also supplied comfortable and trustworthy results for mass and transportation distances, as well as quality measures and others intangible profits. During testing period, simulation model was responsible for a cost reduction of 4.97%, when comparing FY 2005 with FY 2006. Cost was reduced from 1.33 R$/Ton to 1.27 R$/Ton, in 2006. That represents a comparative savings of 7.7 million Reais per year (4 million dollars). As intangible profits for this project, recognized by VALE management team, some can be mentioned as:

  • It supplied a tool for daily decision making within mining environment
  • It allowed the discussion of the mine plan prior to execution
  • It increased significantly the trustworthiness of mine plans to plant managers
  • It allowed equipment utilization analysis such as simulation versus reality
  • It made possible analyses several scenarios in small time interval

已發佈 2008年12月1日

Download the Whitepaper
主題: Arena Simulation Software Mining Simulation Software

Recommended For You

Loading
數位分身模擬可驗證擴展需求
數位分身模擬可驗證擴展需求
Case Study
Case Study
數位分身模擬可驗證擴展需求
Salas O'Brien使用Arena®和Emulate3D™來測試系統是否需要升級,並準確預測食品飲料業客戶所需的投資
CRB 透過模擬和數位分身降低風險
CRB 透過模擬和數位分身降低風險
Case Study
Case Study
CRB 透過模擬和數位分身降低風險
CRB在Emulate3D和Arena技術方面的專業知識,可以協助客戶模擬和測試該解決方案來增加整體設備效率(OEE)。
為什麼要系列化:數位轉型與可追溯性技術
為什麼要系列化:數位轉型與可追溯性技術
部落格
部落格
為什麼要系列化:數位轉型與可追溯性技術
了解可追溯性技術與互聯產品如何改變您的供應鏈管理,並支持您的數位轉型歷程。
  1. Chevron LeftChevron Left Rockwell Automation 首頁 Chevron RightChevron Right
  2. Chevron LeftChevron Left 產品 Chevron RightChevron Right
  3. Chevron LeftChevron Left 軟體 Chevron RightChevron Right
  4. Chevron LeftChevron Left Arena Simulation Software Case Studies Chevron RightChevron Right
  5. Chevron LeftChevron Left Scheduling and Planning with Mine Models Chevron RightChevron Right
請更新您的 cookie 設定以繼續.
此功能需要 cookie 來改善您的體驗。請更新您的設定以允許這些 cookie:
  • 社群媒體Cookie
  • 功能Cookie
  • 性能Cookie
  • 行銷Cookie
  • 全部Cookie
您可以隨時更新您的設定。想了解更多訊息,請參閱我們的 隱私政策
CloseClose